Can I customize the numbering system for financial objects in Procore?

Beta icon For Procore Customers in the United States

flag-us.png When your company applies the 'Owners English' or 'Specialty Contractors English' point-of-view dictionary, you'll see different tool names and term changes in the user interface. Learn how to apply the dictionary options.

  • To learn the differences: Show/Hide

    • This table shows the differences in tool names (bold) and terms across the point-of-view dictionaries for Project Financials. These dictionaries are available in US English only. The default dictionary is designed for general contractors, which means that you will need to work with your Procore Administrator at your company and your Procore point of contact to access the other dictionary options.

      General Contractors English (United States) - Default

      Owners English (Owner Terminology V2)

      Specialty Contractors English (Specialty Contractor Terminology)

      Invoicing

      Invoicing

      Progress Billings

      Owner

      Funding

      Owner

      Owner/Client

      Owner/Client

      GC/Client

      Prime Contract Change Order

      Funding Change Order

      Client Contract Change Order

      Prime Contracts

      Funding

      Client Contracts

      Revenue

      Funding

      Revenue

      Subcontract

      Contract

      Subcontract

      Subcontractor

      Contractor

      Subcontractor

      Subcontractor Schedule of Values (SSOV)

      Contractor Schedule of Values (CSOV)

      Subcontractor Schedule of Values (SSOV)

Answer

Yes. In the Financial Management tools, you can use Procore's default numbering system for financial objects or you can create your own customized numbering system for each object. To learn more, see:

  • About the Financial Management Object Numbering System

  • Best Practices for Custom Numbering Systems

About the Financial Management Object Numbering System

By default, Procore automatically numbers new financial objects sequentially. For example: 001, 002, 003, and so on. For easy identification of project-related commitments, Procore also includes an abbreviation (PO or SC) and a project number in the default numbering system.

Important icon Important

Users with permission to create objects in the Financial Management tools can customize the numbering system for the different financial objects. To do this, overwrite the default entry in the 'Number (#)' field while creating the new object. All future objects will use the customized numbering system and it can customized again the future. To learn about best practices, see Best Practices for Custom Numbering Systems.

Default Numbering & Example Custom Numbering

This table details the default numbering system for each financial object and provides an example of a custom numbering system. For best results, review the important notes before starting any customization.

Procore Tool: Financial Object

Default Numbering System

Example: Custom Numbering System

Important Notes

Change Events: Change Event

001, 002, 003...

CE-001, CE-002, CE-003...

Limited to a maximum of ten (10) characters in length.

Change Orders: Commitment Change Order

001, 002, 003...

CCO-001, CCO-002, CCO-002...

-

Change Orders: Commitment Potential Change Order

001, 002, 003...

CPCO-001, CPCO-002, CPCO-003...

-

Change Orders: Prime Contract Change Order

001, 002, 003...

PCCO-001, PCCO-002, PCCO-002...

-

Change Orders: Prime Potential Change Order

001, 002, 003...

PCPO-001, PCPO-002, PCPO-003...

-

Prime Contracts: Prime Contract

001, 002, 003...

PC-001, PC-002, PC-003...

-

Prime Contracts: Owner Invoice

001, 002, 003...

OWN-001, OWN-002, OWN-003...

-

Commitments: Purchase Order

PO-[Project Number]-001, PO-[Project Number]-002, PO-[Project Number]-003...

ORD-[Project Number]-001, ORD-[Project Number]-002, ORD-[Project Number]-003...

A [Project Number] is included in the default numbering system when using the default Procore Cost Code list and a project number is assigned to the Procore project. If a project is integrated with your ERP system's cost code list, [Project Number] is omitted from the default numbering system. When customizing, do NOT exceed the maximum character limits of your ERP system. Avoid renumbering or switching to a custom numbering after Procore synchronizes with an ERP system.

Commitments: Subcontract

SC-[Project Number]-001, SC-[Project Number]-002, SC-[Project Number]-003...

SubK-[Project Number]-001, SubK-[Project Number]-002, SubK-[Project Number]-003...

A [Project Number] is included in the default numbering system when using the default Procore Cost Code list and a project number is assigned to the Procore project. If a project is integrated with your ERP system's cost code list, [Project Number] is omitted from the default numbering system. When customizing, do NOT exceed the maximum character limits of your ERP system. Avoid renumbering or switching to a custom numbering after Procore synchronizes with an ERP system.

Commitments: Subcontractor Invoice

001, 002, 003...

INV-001, INV-002, INV-003...

-

Best Practices for Custom Numbering Systems

  • Establish a custom numbering system when creating the initial financial object in a Procore project.

  • Avoid renumbering your financial objects mid-project.

  • Avoid switching to a custom number scheme after creating the initial financial object.

  • Inform teammates who create financial objects of all changes to your numbering system.