How are the date columns in submittal custom reports calculated?
Answer
Approver Due Date Variance
When a Submittal is Closed, this column is equal to Approver Return Date - Approver Due Date
When a Submittal is Open, this column is equal to Current Date - Approver Due Date
Approver Returned Date Duration
When as Submittal is Closed, this column is equal to Approver Returned Date - Approver Sent Date
When a Submittal is Open, this column is equal to Current Date - Approver Sent Date
Ball in Court Duration
When a Submittal is Open, this column is equal to Current Date - Ball in Court Sent Date