Set up Configurable Views for the Change Events Line Items View
Objective
To create and manage configurable views for the Change Events tool in Procore.
Background
The default views in the Change Events tool list view are 'Classic Detail', 'Classic Summary', 'Complete View', 'Owner's View' and 'Scope View'. Each view consists of a different arrangement and grouping of columns designed to present the data in the tool in a specific way. A configurable view is created and configured by Procore users when the desired column arrangement for the Change Events tool is not met by the existing default views. Creating configurable views allows users to customize the list view of the Change Events tool with the columns of their choice and save the view so it can be standardized across Procore projects.
Things to Consider
Required User Permissions:
'Admin' level permissions on the Company level Directory tool.
Additional Information:
Newly created views are automatically applied to all projects.
Newly created views are set to 'Hidden' until they are published. See Change the Status of a Configurable Change Events View.
Custom Fields are NOT supported by configurable views.
Steps
Create a New View
Navigate to the Company level Admin tool.
Under 'Tool Settings', click Change Management.
Click the Configurable Views tab.
Click Create View.
Note: To edit an existing view, click the title of the view in on the Configurable Views page.Enter a name and description for the view.
Optional: Select a project from your company to preview the new view with up to 25 rows of data.
Optional: Choose an existing view to use as a template for creating the new view. The new view will automatically be populated with the columns from the selected existing view.
Click Configure View to begin configuring the new view.
Click the configuration icon
to view the list of available columns to add to the view.
Toggle the switches on
to include a column in the view.
Configure Columns
Click the 'Table Settings' icon to open the menu for row height and column configurations.
Row Height:
Choose between small, medium, and large row height for the change events list view.
Configure Columns:
Use the toggle switch to determine which columns will be displayed or hidden from the change events list-view.
Clicking Reset To Default will set all columns to display.
Click and drag column titles to move their position in the table to the left or right.
Click the vertical ellipsis when hovering over a column header/title to open additional column settings:
Group By
Pin Column
Pin Left
Pin Right
Autosize This Column
Autosize All Columns
Reset Columns
View Line Items
The Line Items card on an individual change event lets you perform different viewing and editing functions. To learn about your options, see (Beta) View the Change Events Line Items View.
Change Event Data Columns
Change Event General Information
Number
Shows the change event number that was assigned at creation.Title
Shows the title of the change event.CE Number - Title
The change event number and title combined.Status
Show the current status of the change event. To learn about Procore's default statuses, see What are the default statuses for change events in Procore?Scope
Shows one of the following scope options: In Scope, Out of Scope, or TBD. See What are the default scope options for change events in Procore?Type
Shows the type associated with the change event: TBD, Allowance, Contingency, Owner Change, or Transfer to indicate the type of cost you are preparing for. See Set the Default Change Management Configurations.Change Reason
Shows the reason associated with the change. See Set the Default Change Management Configurations.Origin
Shows a link to the item in a Procore project tool from which the change event originated. See Which Procore tools can I use to create a change event?Date Created
The date the change event was created.Created By
The name of the user who created the change event.
Change Event Detail
Item Type
Shows the type associated with the line item: Line Item, or Markup.Budget Code
Shows the budget code associated with the line item. See What is a budget code in Procore's WBS?Description
Shows the description entered for the individual change event line item.Vendor
The name of the company whose contract(s) is/are potentially affected by the change event line item.Contract
The number and title of the contract being affected by the change event line item.Unit of Measure
The unit of measure selected for the change event line item. See Which units of measure are included on Procore's master list?
Production
Unit of Measure
The unit of measure selected for the measurable amount of work installed on the project that is associated with the change event line item.Quantity
The number of the chosen units of measure associated with the measurable amount of work installed on the project that is associated with the change event line item.
Revenue
Quantity
The number of the chosen units of measure associated with the revenue of the change event line item.Unit Cost
The value assigned to each unit associated with the revenue of change event line item.Revenue ROM
The rough order of magnitude (ROM) is the preliminary revenue value assigned to the change event line item.Prime/Prime PCO
The value of the prime change order SOV line item connected to the change event line item.Prime PCO Title
The title of the change order or potential change order connected to the change event line item.Latest Price
The most up to date value associated with the revenue of the change event line item.
Cost
Quantity
The number of the chosen units of measure associated with the cost of the line item.Unit Cost
The value assigned to each unit associated with the cost change event line item.Cost ROM
The rough order of magnitude (ROM) is the preliminary cost value assigned to the change event line item.Request for Quote
The value of a returned RFQ associated with the change event line item.RFQ Title
The title of an RFQ associated with the change event line item.Commitment/Commitment CO/PCO
The value of the commitment or commitment change order SOV line item connected to the change event line item.Commitment Title
The title of the of the contract or change order connected to the change event line item.Latest Cost
The most up to date value associated with the cost of the change event line item.Over/Under
The difference between the 'Latest Price' and the 'Latest Cost'.
Budget
Quantity
The number of the chosen units of measure associated with the budget of the change event line item.Unit Cost
The value assigned to each unit associated with the budget of the change event line item.Budget ROM
The rough order of magnitude (ROM) is the preliminary value assigned to a budget change connected to the change event line item.Budget Change
The value of the budget change connected to the change event line item.Latest Budget Impact
The most up to date value for the budget impact of the change event line item. The value will match the Budget ROM column or the Budget Change column if there is a value.
Filter and Sort the Line Items View
Filtering
Click the Filters at the top of the change events table.
Select from the following filters:
Status
Scope
Type
Change Reason
Sorting
Click the title of a column to change its sorting behavior.Example: Change the sorting order of the 'Status' column so Open Change events are listed first.
Grouping Columns
Column grouping allows you to better organize the Change Events line items table, especially when it comes to evaluating financial risk in your project. Specify which columns you would like to group and items within that group will roll-up underneath.
To group columns, click the Select Group selector at the top of the change events table and select the columns you want to group together.
If more than one grouping is selected, they can be rearranged within the 'Group By' Selector by clicking and dragging them into the preferred order. A grouping can be deleted by clicking the 'x' on the right side of the group.
Groupings can be reset by clicking Reset at the bottom of the selector.
Change the Status of a Configurable Change Events View
The status of individual configurable views can be toggled between Published and Hidden. Published views are available for use on their assigned projects and hidden views are not available for use. The hidden status is useful for when a configurable view is in creation but not ready to be implemented.
Navigate to the Company level Admin tool.
Under 'Tool Settings', click Change Management.
Click the Configurable Views tab.
Click the Status column in the row of the view being changed.
Duplicate or Delete a View
Configurable views can be duplicated to make building a new view easier. Duplicating a view creates a new view that is an exact copy of the existing view. Deleting a view removes the view permanently.Note: Deleted views are NOT recoverable. Procore's default views cannot be deleted.
Navigate to the Company level Admin tool.
Under 'Tool Settings', click Change Management.
Click the Configurable Views tab.
Click the ellipsis icon in the row of the view being changed.
Click Duplicate or Delete.