Clone a Change Event
Objective
To clone a change event.
Background
If you need to create a new change event that is identical or nearly identical to an existing one, you can create a clone. A clone is an exact copy of an existing change event that you can then modify as needed.
Things to Consider
Required User Permissions:
'Admin' level permissions on the project's Change Events tool.
Prerequisites
Steps
Navigate to the project's Change Events tool.
Locate the change event using one of these options:
Click the Detail tab. Then click the change event link that you want to work with.
ORClick the Summary tab. Then click the View button.
Click the Clone button.
You will be taken to the cloned change event with the following information copied over from the first change event:Type
Description
Attachments
Title
Scope
Change Reason
Cost Code
Cost Type
Description
Vendor
Contract