Add Scheduled Work Log Entries (Android)

Objective

To add Scheduled Work entries to the Daily Log using the Procore app on an Android mobile device.

Things to Consider

  • Required User Permissions:

  • Additional Information:

    • Entries made by collaborators are marked as 'pending' until approved by an administrator.

    • There are additional workforce labor categories that can be added to the Daily Construction Report in the Daily Log: (e.g. Women, Veteran, Minority, First-Year Apprentice, Local (City), and Local (County)). In order to track hours for these additional workforce labor types, these fields must first be configured in the Daily Log section of the Company Admin tool, and then applied to one or more projects. See How do I enable additional workforce labor types for the Daily Log?
      Note: After configured and applied, a 'Workforce Hours' column will be available with a link to 'Add Hours' link will appear in the Daily Construction Report section.

  • You can configure what items are created with the quick create icon-plus-quick-create-mobile2.png icon, see Configure Quick Create Settings.

  • This action can be performed in offline mode. Tasks performed in offline mode sync with Procore once a network connection is reestablished.

Steps

  1. Open the Procore app on an Android mobile device and select a project.
    Note: This loads the Tools screen for the project.

  2. Tap the quick create icon-plus-quick-create-mobile2.png icon and select Scheduled Work.
    OR
    Tap the **Daily Log tool. Tap the create icon-plus-quick-create-mobile2.png icon, then tap Work Entry.

  3. Tap into the following fields to enter the relevant information:

  4. Tap Save.

Tip icon Tip

If required fields are empty, click Fix Errors to go to the first empty field. Click Next Field or Previous Field to view other empty required fields.

After the required fields have been entered, you will be able to create or save the form.