Configure Advanced Settings: Direct Costs
Objective
To configure the advanced settings for the project's Direct Costs tool.
Background
Users with the appropriate permissions to the Direct Cost tool can configure a variety of advanced settings for your project.
Things to Consider
Required User Permissions:
'Admin' level permissions on the project's Direct Costs tool.
Prerequisites
Steps
Set User Permissions for the Direct Costs Tool
Navigate to the project's Direct Costs tool.
Click Configure Settings
.
Set the access permission level for the tool's users by clicking the icon in the desired column so a GREEN checkmark appears.
The color-coded icons in the user permissions area denotes the user's access permission level to the tool. To learn more, see What are the default permission levels in Procore?
Icon
Color
Definition
GREEN
The user has been granted this access permission level to the tool.
RED
The user has NOT been granted this access permission to the tool.
GREY
The user is either a Procore Administrator or has been granted permissions to the Procore tools on this project using a permissions template (see What is a permissions template?). To change the user's permission level to this tool, see Manage Project Permissions Templates.