Delete a CCO Synced with ERP
ERP DOCUMENTATIONEach Procore-built ERP integration offers its own unique feature set. Your integration might not support the action described on this page.
To learn about your integration and its supported features, see Things to Know About Your ERP Integration.
To explore all documentation for your integration, see ERP Integrations.
Each Procore-built ERP integration offers its own unique feature set. Your integration might not support the action described on this page.
To learn about your integration and its supported features, see Things to Know About Your ERP Integration.
To explore all documentation for your integration, see ERP Integrations.
Objective
To delete a Commitment Change Order (CCO) from a Procore project after it has been synced with your ERP integration.
Background
After syncing a CCO with your ERP system, users will typically follow the change order process when a CCO needs to be modified. However, you might sometimes need to delete a synced CCO on a project. Since Procore does not allow deletion of synced commitments, you must first unlink the records in the two systems before you can delete the CCO.
Things to Consider
Required User Permissions:
'Admin' level permissions on the project's Commitments tool.
Limitations:
You cannot delete an 'Approved' change order. See Why can't I edit or delete an approved change order?
After a synced CCO is unlinked and deleted, the data is permanently removed from the system and cannot be restored.
Prerequisites:
Prerequisites vary depending on which ERP system your account is integrated with. For most integrations, deletion of the item in the ERP system is a prerequisite for unlinking in Procore. To learn more about your specific integration, see Things to Know about your ERP Integration.
Unlink CCOs Synced with ERP before attempting to delete.
Requirements, limitations, and considerations will vary depending on the ERP system your Procore account is integrated with. See Things to Know about your ERP Integration for details.
Steps
Navigate to the project's Commitments tool.
Note: Before proceeding, make sure the CCO is unlinked. See Unlink CCOs Synced with ERP.Locate the synced CCO in the list.
Click View or Edit.
Update status to Draft.
Click Save.
Return to the project's Commitments main tool page.
Locate the CCO that you want to delete. Click Delete
.