Copy or Move a Group to Another Estimate
Objective
To copy or move a group to another estimate in the Estimating, Bid Board, or Portfolio Planning tool.
Things to Consider
Required User Permissions for the Bid Board tool.
Required User Permissions for the Estimating tool.
Required User Permissions for the Portfolio Planning tool.
This feature is only available when there is more than one estimate in the project. If there is only one estimate, you will see 'Copy Here' instead of 'Copy to Other Estimate'.
Steps
Navigate to the Bid Board or Portfolio Planning tool and select the project.
OR
Navigate to the project's Estimating tool.Follow the relevant steps below:
Copy a Group from an Estimate
Copy a Group from a Takeoff
Move a Group from an Estimate
Move a Group from a Takeoff
Copy a Group
From an Estimate
Locate the group that you want to copy to another estimate.
Click the vertical ellipsis
icon for the group.
Hover over Copy to Other Estimate.
Click the estimate that you want to copy the group to.
The group is automatically added to the selected estimate.
From a Takeoff
Click the Takeoff tab.
Locate the group that you want to copy to another estimate.
Click the vertical ellipsis
icon for the group.
Hover over Copy to Other Estimate.
Click the estimate that you want to copy the group to.
The group is automatically added to the selected estimate.
Move a Group
From an Estimate
Click the Estimating tab.
Locate the group that you want to move to another estimate.
Click the vertical ellipsis
icon.
Hover over Move to Other Estimate.
Click the estimate that you want to move the group to.
The group is automatically added to the selected estimate.
From a Takeoff
Click the Takeoff tab.
Locate the group that you want to move to another estimate.
Click the vertical ellipsis
icon.
Hover over Move to Other Estimate.
Click the estimate that you want to move the group to.
The group is automatically added to the selected estimate.