Adjust Retainage by Line Item in Portfolio Financials
NoteThis information is intended for accounts with Portfolio Financials product in Procore. Please reach out to your Procore point of contact for more information.
This information is intended for accounts with Portfolio Financials product in Procore. Please reach out to your Procore point of contact for more information.
Objective
To adjust retainage by line item in Portfolio Financials.
Background
When retainage is enabled for a contract in Portfolio Financials, both owners and vendors can adjust the amount retained by line item when submitting invoices.
Things to Consider
Required User Permissions:
'Vendor' access to the project or higher.
Note: Users with 'Vendor' or 'Limited' permissions must have access to the contract in order to adjust retainage.
Steps
Navigate to the relevant Contract Room by clicking the name of the cost item in the project's Cost Tracker.
Note: Cost items with a Contract Room are marked with a ribbonicon.
Click the Invoices tab.
Click the invoice you want to adjust retainage for.
OR
Click Add Invoice to add a new invoice. See Add an Invoice in Portfolio Financials.In the 'Retainage This Period' column, click Adjust.
Edit percentages in the 'Retainage' column as necessary.
Click Save.