Update the Percent Complete for a Schedule Task (iOS)

Objective

To update the Percent Complete field in the project Schedule tool using an iOS mobile device.

Things to Consider

  • Required User Permissions:

    • 'Admin' level permissions on the Project level Schedule tool.
      OR

    • 'Read Only' or 'Standard' level permissions with the 'Update Task Completion Percentages' granular permission enabled on the permission template.

  • Additional Information:

Prerequisites

Steps

  1. Navigate to the project Schedule tool using an iOS mobile device.

  2. Tap the schedule task you want to update.

  3. Tap Edit.
    edit-schedule-item-ios.png
    Note: Percent Complete cannot be updated for Summary schedule tasks or Milestones.

  4. Enter the current percent complete for the task and tap Done.
    Note: You can enter a numeric value from 0 to 100. The value enter must be a whole number.

  5. Tap Save.
    save-scheduled-item-ios.png

  6. The schedule task on the mobile device updates to show the amount you entered for Percent Complete.
    schedule-item-percent-saved-ios.png
    Note: These changes are also shown in the Schedule tool on the web application.