View the Change History of Lookaheads
Objective
To view the change history of Lookaheads changes made in Procore.
Things to Consider
Required User Permissions:
'Admin' level permissions on the Project level Schedule tool.
OR'Read Only' level permissions or higher on the Project level Schedule tool with the 'View the Change History of a Lookahead' granular permission enabled on your permissions template.
Additional Information:
Items cannot be deleted from the change history.
The change history outlines the following actions performed:* Lookahead subtask created* Who created* What time created* Lookahead task deleted* Who deleted* Time deleted* Start date updated* Who updated* Time updated* Finish date updated* Who updated* Time updated* Lookahead task status* Work complete
Ex. Tasks going from light red to dark red* Work incomplete
Ex. Tasks going from dark red to light red* Work started: Tasks go from blank to light red* Time
Prerequisites
Steps
Navigate to the Project level Schedule tool.
Click the Lookaheads tab.
Click the schedule creation button to show the Activity Feed panel.
The activity feed shows the change history of the entire Lookahead.
Note: Users can only view change history for the entire Lookahead not individual activities.