Work Breakdown Structure Setup

The first step when setting up Procore's Project Financials tools in a Procore project is to create your company's Work Breakdown Structure. You also have the option to create a unique project level WBS.

Background

Procore's default Work Breakdown Structure includes two (2) default segments: cost code and cost type. It also includes an optional sub job segment that lets you add sub jobs to a project. Segments are the building blocks that define your company's budget code structure. To learn more about segments, see What are segments and segment items?

  • Default: Cost Code Segment. Procore's default 'Cost Code' segment is a tiered segment that aligns with the 17 Division cost code structure of the CSI MasterFormat®. See What are Procore's Default Cost Codes? You can use the default cost codes or you can customize your cost code segment by adding cost codes manually as segment items. You can also import your cost codes using the Procore Imports app. The import process allows you add or edit segment items but cannot be used to delete any existing segment items.

  • Default: Cost Type Segment. In Procore, cost types are a way to identify and classify your project's job costs. They can also be used to generate reports. To learn more, see What are Procore's default cost types?

  • Optional: Sub Job Segment. In Procore, a sub job allows you to compartmentalize job costs within a project. Once they are added to Procore (or imported via an integrated ERP system) you can monitor your project budgets and costs against them to help you better determine if you are making money on your project.

  • Optional: Custom Segments. Your company can name custom segments anything you want. You can also define the number of alphanumeric characters you want to represent each segment's coding scheme. Custom segments can also be combined with Procore's default segments when configuring your company's budget code structure.

Many companies design their budget code structure to align with the CSI MasterFormat. Other companies decide to implement a budget code structure that is unique to their industry, organization, or project environment. Regardless of the structure, you can perform your own imports using the Procore Imports app. You can also Request to Import Segment Items for WBS.

To learn more about WBS, see the Work Breakdown Structure landing page. We recommend reading About Work Breakdown Structure and reviewing the steps in Create Your Company's Default Work Breakdown Structure and Create Your Project's Work Breakdown Structure with your team.