Add the Columns for the 'Budget Changes' Feature to a Budget View
Phased ReleaseThe new Budget Changes feature is designed to replace the existing budget modifications feature. Once you migrate to Budget Changes, you will no longer have access to the budget modifications feature. If you have any questions before your company starts the migration, contact your Procore point of contact. To learn more about the timeline for migration, see: Common Questions.
The new Budget Changes feature is designed to replace the existing budget modifications feature. Once you migrate to Budget Changes, you will no longer have access to the budget modifications feature. If you have any questions before your company starts the migration, contact your Procore point of contact. To learn more about the timeline for migration, see: Common Questions.
Objective
To add the recommended columns for the 'Budget Changes' feature to a Procore budget view.
Background
Procore's 'Budget Changes' functionality provides project managers with greater control and insight into changes that impact your budget. Whether it's an increase, decrease, or net zero (0) budget change, this feature eliminates the need to create a separate budget line item in Procore. It also allows you to reflect the true cost and revenue of your change on a project's budget.
Things to Consider
Required User Permissions:
'Admin' level permissions on the Company level Admin tool.
Additional Information:
To learn more about budget changes in Procore, see Create Budget Changes.
Prerequisites
Add the Budget and Change Events tool to the project. See Add and Remove Project Tools.
Configure the 'Budget ROM' column settings in the Change Events tool. See Configure Settings: Change Events.
Steps
Step 1: Add or Modify a Budget View
Step 2: Add the Source Columns for the Budget Changes Feature
Step 3: Modify the Calculated Columns for the Budget Changes Feature
Step 4: Preview the Budget View
Step 5: Assign the Budget View to Your Projects
Step 1: Add or Modify a Budget View
When adding the columns detailed in this article, you have these choices:
You can create a new budget view and add the recommended columns. See Set Up a New Budget View.
You can edit an existing budget view and add the recommended columns. See Edit an Existing Budget View.
You can set up a budget view to use with Procore custom reports and add the recommended columns. See Set Up a Budget View for Custom Reporting.
After choosing the preferred option for your budget view, add all of the recommended columns using the steps detailed below.
ExampleFor the next steps, we created a new budget view based on the Procore Standard Budget view, which is at the top of the list under 'Standard Views'.

We also named our new view 'Budget Changes'. However, you can name your budget view as you want. When you are ready to continue, click the Configure Columns button. Then proceed by adding the recommended source and calculated columns.

For the next steps, we created a new budget view based on the Procore Standard Budget view, which is at the top of the list under 'Standard Views'.
We also named our new view 'Budget Changes'. However, you can name your budget view as you want. When you are ready to continue, click the Configure Columns button. Then proceed by adding the recommended source and calculated columns.
Step 2: Add the Source Columns for the Budget Changes Feature
You will begin by adding the recommended source columns as follows:
Add the 'Budget ROM' Source Column
Add the 'Budget Changes' Source Column
Add the 'Budget ROM' Source Column
In the 'Configure Columns' window, follow these steps to add a new source column named 'Budget ROM'. This column allows your team to forecast the potential impact that a change may have on your budget. Depending on the 'Budget ROM' settings in the Configure Settings page of the Change Events tool, you can configure this column to reflect the Rough Order of Magnitude value in your budget as Cost or Revenue. To learn more, see Configure Settings: Change Events and What is the 'Budget ROM' column in Procore's Budget tool?
Steps from the Configure Columns window in the Company Admin tool… | Settings |
---|---|
|
Add the 'Budget Changes' Source Column
In the 'Configure Columns' window, follow these steps to add a new source column named 'Budget Changes'.
Steps from the Configure Columns window in the Company Admin tool… | Settings |
---|---|
|
Step 3: Modify the Calculated Columns for the Budget Changes Feature
Next, you will modify the existing calculated columns (or add new ones) to include the new source columns in the calculated columns formulas.
Add or Modify the 'Revised Budget' Calculated Column
Add the 'Projected Cost Budget' Calculated Column
Add or Modify the 'Revised Budget' Calculated Column
In the 'Configure Columns' window, follow these steps to modify the existing 'Revised Budget' column for the budget changes feature. Adding this column allows your project team to see the impact of the change on your budget.
Steps from the Configure Columns window in the Company Admin tool… | Settings |
---|---|
|
Add the 'Projected Cost Budget' Calculated Column
In the 'Configure Columns' window, follow these steps to add a calculated column named 'Project Cost Budget'. Adding this column allows you to include budget changes so your team can track the projected cost to completion on the project's Budget tool.
Steps from the Configure Columns window in the Company Admin tool… | Settings |
---|---|
|
Step 4: Preview the Budget View
Next, you can preview your new columns in the 'Column Configuration' area and by selecting different projects in the 'Preview with Project' drop-down list. The new columns appear on the right side of the budget. Finally, you can assign the budget view to one or more Procore projects in your company's account using the options in the 'Assign to Projects' drop-down list.
ExampleBelow is an example of the new columns that you can add to a Procore budget view, after it has been assigned to a project.

Below is an example of the new columns that you can add to a Procore budget view, after it has been assigned to a project.
Step 5: Assign the Budget View to Your Projects
When you are ready to proceed, assign the budget view to one, multiple, or all projects. Simply select the options in the 'Assign to Projects list.