Create a Commitment Potential Change Order

Objective

Background

When a change to the scope of work or the original commitment contract amount occurs during a construction project, the change management process begins. You can create a PCO if your company's Procore Administrator configures the Commitments tool with the two (2)- or three (3)-tier change order configuration setting. See What are the different change order tier settings in Project Financials?

Things to Consider

  • Required User Permissions:

  • Additional Information:

  • Limitations:

    • To create a change order for a commitment, the commitment must be in the 'Approved' status.

  • For companies using theicon-erp-synced2.pngERP Integrations tool: Show/Hide

Prerequisites

Steps

  • Create a Potential Change Order

  • Add a Schedule of Values to a Potential Change Order

Create a Potential Change Order

  1. Navigate to the project's Commitments tool.

  2. Locate the commitment contract to work with. Then click its Number link.

  3. Click the Change Orders tab.

  4. Click Create Potential CO.
    create-potential-change-order-from-prime-contract.png

  5. Complete the following fields:

    • Sign with DocuSign®
      If you have enabled the Procore + DocuSign® integration (see Enable or Disable the DocuSign® Integration on a Procore Project), a checkmark appears in this box by default. If you do NOT want to collect signatures with DocuSign®, remove the mark.

      Tip icon Tip

      How do you collect signatures with DocuSign? After the data entry for the item is complete, Procore recommends changing the item's status to 'Out for Signature' before clicking the Complete with DocuSign button to launch the DocuSign® application. If you have not previously signed in, you will be prompted to Log In to DocuSign®. Once you are signed in, you can prepare the DocuSign_®_ envelope for signatures. After the signature process is complete, Procore automatically changes the status of the item to 'Approved' and marks the item as 'Executed'. To learn more, see DocuSign®.

    • Number
      Accept the default number, enter a new number, or create a custom numbering scheme.

      Tip icon Tip

      How are numbers assigned? To learn how Procore assigns numbers and to understand your custom numbering options, see Can I customize the numbering system for financial objects in Procore?

    • Date Created
      Shows the creation date and time. This value cannot be changed.

    • Revision
      Shows the revision number. The first version is zero (0), subsequent revisions are assigned in sequential order. A PCO might have several revisions, depending on its reviewer/approver feedback.

    • Created By
      Shows the Procore user who created the PCO. This value cannot be changed.

    • Contract Company
      Shows the name of the company responsible for performing the work on the contract.

    • Contract
      If you have been assigned access permissions to the Commitments tool, click this link to open the contract.

    • Title
      Enter a title for the PCO in this box.

    • Status
      Select the current state of the PCO. To learn more, see What are the default statuses for change orders in Procore?

    • Commitment Change Order
      Choose one (1) option button.

      Note icon Note

      This setting is only required when the Commitments tool is using the 3-Tier change order configuration setting. See What are the different change order tier settings in Project Financials?

      • None. A PCO can be linked to a COR at a later time.

      • Add to Existing. Link the PCO to an existing COR.

      • Create New. Create a new COR. You also have the option to create a new change order at the same time.

    • Change Reason
      Select the reason for the PCO, either Client Request, Design Development, Allowance, Existing Condition, Back Charge, or any additional options created for your specific environment by your company's Procore Administrator. See Set the Default Change Management Configurations.

    • Private
      Mark this checkbox if you only want the PCO to be visible to users with 'Admin' permissions on the Commitments tool.

    • Accounting Method
      This field inherits the accounting method that was specified in the commitment contract. See How do I set the accounting method for a contract or funding?

    • Description
      Enter a more detailed description of the reason for the PCO.

    • Request Received From
      Select the Procore user for whom you are submitting the PCO.

    • Schedule Impact
      If known, provide an estimate for the additional number of days required to complete work when the PCO is approved.

      Beta icon In Beta

      Note to users participating in the 'Subcontractor Estimated Completion' limited release beta program. When a user places a change order in the 'Approved' status and it includes a value in 'Schedule Impact' field of the change order, Procore automatically updates the 'Estimated Completion Date' field in the commitment contract by the number of days entered. To learn more about this program, see Commitments: (Beta) Subcontractor Estimated Completion Date.

    • Location
      Use this drop-down list to select a location related to the PCO. You can select an existing location or Add a Multi-tiered Location to an Item.

    • Reference
      Add any other important tools, materials, drawings, or documents to use as a reference for the PCO.

    • Field Change
      Check this box if the PCO requires a field change.

    • Paid in Full
      Check this box to indicate you have received payment for this change.

    • Attachments
      Select and add any relevant documents.

  6. Click Create & Enter SOV.

Add a Schedule of Values to a Potential Change Order

When there are costs associated with a PCO, you must add line items to the SOV.

  1. In the Schedule of Values tab, click Add Line.

    Note icon Notes

  2. For contracts using the Amount Based accounting method:

    • Change Event Line Item
      If you have change events enabled, you can select a change event line item if the commitment needs to be linked to a change event.

    • Budget Code
      Select a budget code from the list or click Create Budget Code to create a new one. See What is a budget code in Procore's WBS?

    • Description
      Enter a description for the line item. For example, type: Monthly Service Fee

    • Amount
      Enter the amount of the cost.

    • Billed to Date
      The system automatically calculates the amount billed on the commitment up to the current date.

    • Amount Remaining
      Enter the amount that has NOT been billed to the current date.

    • Tax Code
      Enter a tax code to use for this line item. This field only appears if you have enabled the tax codes feature. See How can I use tax codes on a project?

  3. For contracts using the Unit/Quantity Based accounting method:

    • Change Event Line Item
      If you have change events enabled, you can select a change event line item if the commitment needs to be linked to a change event.

    • Budget Code
      Select a budget code from the list or click Create Budget Code to create a new one. See What is a budget code in Procore's WBS?

    • Description
      Enter a description for the line item. For example, type: Monthly Service Fee

    • Qty
      Enter the number of units.

    • UOM
      Enter the Unit of Measure (UOM).

      Note icon Notes

    • Unit Cost
      Enter the Unit Cost in the box provided.

    • Amount
      The system automatically calculates the subtotal for you, based on the Qty, UOM, and Unit Cost entries.

  4. Click Save.
    A GREEN banner appears to indicate that the Schedule of Values is saved.

    Important icon Important

    If you assigned a budget code that is not currently represented on your budget or if leave the budget code field blank, a confirmation message appears. To proceed, you must click OK to acknowledge the message. This action adds the corresponding line item(s) to your project's budget as non-budgeted line items.

Next Steps