Detailed Data Mapping

Note icon Note

The below fields are supported in Procore. Additional or custom fields added in Primavera will not sync to Procore.

Gantt View

In Procore, the Gantt chart reads directly from the native schedule file. The chart below shows how each field imports data from Primavera (Primavera Cloud, P6) to Procore. You can find the Gantt view in the Gantt section of the Project Schedule tool. See View a Gantt Schedule.

PROCORE Field Name

Imports data from Primavera (Primavera Cloud, P6) to Procore

Primavera (Primavera Cloud, P6) Field Name

Activity ID

tri-left-arrow-green.png

Activity ID

Task Name

tri-left-arrow-green.png

Activity Name

Baseline Start

tri-left-arrow-green.png

Baseline Start1

Baseline Finish

tri-left-arrow-green.png

Baseline Finish1

Start

tri-left-arrow-green.png

Start

Finish

tri-left-arrow-green.png

Finish

Duration

tri-left-arrow-green.png

At Completion Duration

% Complete

tri-left-arrow-green.png

Duration, % Complete, Physical % Complete, Units % Complete2

Predecessors

tri-left-arrow-green.png

Predecessors

Successors

tri-left-arrow-green.png

Successors

WBS3

tri-left-arrow-green.png

WBS

Resources

tri-left-arrow-green.png

Resource Assignments4

ID5

Note: Blank import fields on the chart indicate the fields do not map to Procore.

1 Imports vary as described below:

  • If the user has set the "Project Baseline" in Primavera to be "Current Project" (which is the default value) then we will populate the baseline fields appropriately when reading from XER and PMXML files. No special action required on the part of the user.
    Note: Using 'Current Project' in Primavera will assume the 'Planned start' and 'Planned Finish' dates as the 'Baseline Start' and 'Baseline Finish' dates.

  • If the user has selected a specific project under the "Project Baseline" setting in Primavera and an XER file is being used, we will not populate the baseline fields (the data won't be present in the XER file).

  • Data will only be accurate when 'Budgeted values with planned dates' is selected for the "Earned Value Calculation" setting in P6.

  • If the user has selected a specific project under the "Project Baseline" setting in Primavera and a PMXML file is being used, and the user has remembered to include the baseline project in the export, the baseline fields will be populated.

  • Only one Baseline Start and Baseline Finish is supported in Procore.

2 Default settings in Primavera allows users to identify which % complete they want to used as the default. Whichever percent setting they choose will be the one pulled into Procore from Primavera.

3 Work Breakdown Structure (WBS). WBS tasks use 'Duration % Complete' in Procore.

4 Procore determines which resources are associated with a task by reading the resource assignment information from a Primavera schedule.

5 ID is originally pulled in for sequential numbering based scheduling software like Microsoft Project. This field does not integrate with Primavera.

Schedule Task Details

The task items details page is a list of all scheduled tasks, as well as their resource, WBS, start and finish date, and percentage complete. You can view the Task Items Details page in the List section of the Project level Schedule tool. See View a Schedule Task.

PROCORE Field Name

Imports data from Primavera (Primavera Cloud, P6) to Procore

Primavera (Primavera Cloud, P6) Field Name

Activity ID

tri-left-arrow-green.png

Activity ID

Activity Name

tri-left-arrow-green.png

Activity Name

Baseline Start

tri-left-arrow-green.png

Baseline Start1

Baseline Finish

tri-left-arrow-green.png

Baseline Finish1

Start

tri-left-arrow-green.png

Start

Finish

tri-left-arrow-green.png

Finish

Duration

tri-left-arrow-green.png

At Completion Duration

% Complete

tri-left-arrow-green.png

Duration, % Complete, Physical % Complete, Units % Complete2

Predecessors

tri-left-arrow-green.png

Predecessors

Successors

tri-left-arrow-green.png

Successors

Notes

tri-left-arrow-green.png

Notes

WBS3

tri-left-arrow-green.png

WBS

Resource

tri-left-arrow-green.png

Resource Assignments4

Actual Start

tri-left-arrow-green.png

Actual Start

Actual Finish

tri-left-arrow-green.png

Actual Finish

Start Variance

tri-left-arrow-green.png

Start Variance

Finish Variance

tri-left-arrow-green.png

Finish Variance

1 If the user has set the "Project Baseline" in Primavera to be "Current Project" (which is the default value) then we will populate the baseline fields appropriately when reading from XER and PMXML files. No special action required on the part of the user.
* If the user has selected a specific project under the "Project Baseline" setting in Primavera and an XER file is being used, we will not populate the baseline fields (the data won't be present in the XER file).
* If the user has selected a specific project under the "Project Baseline" setting in Primavera and a PMXML file is being used, and the user has remembered to include the baseline project in the export, the baseline fields will be populated.

2 Default settings in Primavera allows users to identify which % complete they want to used as the default. Whichever percent setting they choose will be the one pulled into Procore from Primavera.

3 Work Breakdown Structure (WBS). WBS tasks use 'Duration % Complete' in Procore.

4 Procore determines which resources are associated with a task by reading the resource assignment information from a Primavera schedule.

Lookaheads

Lookaheads allows users to create schedule subtasks based off their native schedule file. Lookaheads operates separate from the native schedule and modifications to a Lookahead do NOT impact the native schedule. Lookaheads can be created to range from 1-6 weeks. See Create a Lookahead Schedule.

PROCORE Field Name

Imports data from Primavera (Primavera Cloud, P6) to Procore

Primavera (Primavera Cloud, P6) Field Name

Activity ID

tri-left-arrow-green.png

Activity ID

WBS

tri-left-arrow-green.png

WBS1

Task Name

tri-left-arrow-green.png

Activity Name

Start

tri-left-arrow-green.png

Start

Finish

tri-left-arrow-green.png

Finish

Resource

tri-left-arrow-green.png

Resource Assignments

Notes

Notes2

Company3

Assignees3

ID4

Note: Blank import fields on the chart indicate the fields do not map to Procore.

1 Work Breakdown Structure (WBS)

2 The Notes column will map to the Gantt chart column not the Lookaheads note column.

3 Company and Assignee will pull from the Project Directory.

4 ID is originally pulled in for sequential numbering based scheduling software like Microsoft Project. This field does not integrate with Primavera.