Background

In the construction industry, a submittal is written and/or physical information provided by subcontractors to the general contractor and then to the design team for approval of equipment, materials, etc. before they are fabricated and delivered to the project. Submittals can be presented in various formats, such as shop drawings, cut sheets on equipment, and material samples. Submittals are required primarily for the architect and engineer to verify that the correct products and quantities will be installed on the project in compliance with the design documents/contract documents.

In Procore, a submittal manager is a person responsible for overseeing a submittal throughout its lifecycle. If you create a submittal and have 'Standard' or 'Admin' level permission to the Submittals tool, your name appears as the 'Submittal Manager' by default. However, users with 'Admin' level permission to the Submittals tool have the ability to assign the submittal manager role to any Procore user who has been granted 'Standard' or 'Admin' level permission to the Submittals tool (Note: Users with 'Standard' permission do not have permission to change the submittal manager). The 'Submittal Manager' field lets you change ownership of a submittal when the person who created a submittal (or that submittal's current manager) is no longer a member of the project team.

Although every company and project may have its specific process, it is common for the project manager or engineer to be responsible for acting as the submittal manager. First, the submittal manager will create the submittal. Next, the subcontractor provides the required documentation for the submittal. Then, when the required documentation is in place, the submittal is sent to the appropriate design team members for review and approval.

Things to Consider

Video

Steps

  1. Navigate to the project's Submittals tool.

  2. Click + Create > Submittal.

  3. Create a new submittal as follows:

​Add General Information

Note icon Note

Users with Standard permission to the Submittals tool are limited to viewing the following fields when creating a new Submittal:

Title, Spec Section, Number & Revision, Submittal Type, Responsible Contractor, Received From, Final Due Date, Location, Linked Drawings, Distribution List, Ball in Court, Private, Description, Attachments

  1. Complete the data entry in the General tab as follows:

Notes:If a submittal is Open and has no workflow, the Ball in Court is the Submittal Manager and the item should show in their My Open Items tool.If a submittal is Open and does have a workflow, the current workflow step assignee has the Ball in Court. Once the workflow is complete, BIC returns to the Submittal Manager.If a submittal is Closed, the Ball in Court is cleared.

  • Notes:
    When the 'Final Due Date' occurs, the system sends an automated email notification to notify users that the submittal is overdue. If your system is configured to use sequential approval, the notification goes to the Submittal Manager and the Ball in Court person on the approval workflow. If your system is configured to use parallel approval, the notification goes to the Submittal Manager and members of the approval workflow).

back to steps

Calculate Submittal Schedule Information (If Enabled)

Submittal Schedule Calculations is an optional feature that you can enable. See Enable Submittal Schedule Calculations. When enabled, the Submittals tool will analyze your entries in the 'Required On-Site Date', 'Lead Time', 'Design Team Review Time', and 'Internal Review Time' fields to provide suggestions for the Submitter and Approver 'Due Date' on the submittal workflow. It also automatically populates the 'Planned Return Date', 'Planned Internal Review Completed Date', and 'Planned Submit By Date' fields.

  1. Follow the steps in .
    This reveals the New Submittal page.

  2. Scroll down to the Submittal Schedule Information area.

  3. Set the following information:

    1. Schedule Task. The schedule task associated with the submittal being created. A schedule must be uploaded to the project first. See Upload a Project Schedule File to Procore's Web Application.

    2. Note: If you enter 7, the system subtracts '7' calendar days from the Planned Return Date to automatically populate the date entry for the Planned Internal Review Completed Date.

    3. Note: If you enter 10, the system subtracts '10' calendar days from the Required On-Site Date to automatically populate the date entry for the Planned Return Date.

    4. Note: If you enter 5, the system subtracts '5' calendar days from the Planned Internal Review Completed Date to automatically populate the date entry for the Planned Submit by Date.
      This illustration shows you an example of these entries and calculations.

      create-submittal-schedule-info.png

back to steps

Update the Delivery Information

  • Anticipated Delivery Date
    View the date displaying in the Anticipated Delivery Date. This is the date between the 'Lead Time' and when the submittal was distributed, and it will not populate upon the creation of the submittal. This date is calculated by Procore once the submittal has been distributed. See Distribute a Submittal.​​

  • Schedule Task
    If you have enabled the Schedule tool on the project and integrated an Asta Powerproject, Microsoft Project, or Oracle Primavera schedule with Procore, you are permitted to select a project task from the Schedule Task drop-down list when you have a user account that has been granted 'Read-Only' level permission or higher on the Schedule tool. This is for reference only.

  • Confirmed Delivery Date
    Select the date the subcontractor or supplier confirmed the freight would arrive using the Confirmed Delivery Date calendar.

  • Actual Delivery Date
    Select the date the material arrived on site using the Actual Delivery Date calendar. Typically, this value is updated by the project superintendent.

back to steps

Apply a Submittal Workflow Template

A user with 'Admin' level permission to your project's Submittals tool can create one (1) or more submittal workflow templates which you can then to a new submittal when you first create it. This saves data-entry time by preventing you from having to add a new submittal workflow each time you create a submittal.

  1. Under Submittal Workflow, do the following:

    submittal-workflow-add-template.png

    1. Select a Template. Select a workflow template from the drop-down list.
      Notes:

      • This drop-down list is only visible and available to users with 'Admin' level permission on the Submittals tool.

      • This action applies the person(s) named on the submittal workflow template to your submittal.

      • To learn how submittal workflow templates are created, see Manage Submittal Workflow Templates.

  2. Continue by modifying the Name, Role, and Days to Submit/Response fields as needed for the submittal. Your changes only affect the workflow on the submittal, your changes do NOT affect the submittal workflow template.

  3. (Optional) Continue with the steps in Add Users to the Submittal Workflow.

Add Users to the Submittal Workflow

  1. Under Submittal Workflow, do the following for each desired line item in the submittal:

    • Name. Start typing a project user's name in the Search box. Then select the appropriate user from the list.* If you want to require a response from the user, place a mark in the checkbox next to their name.
      OR* If you do NOT want to require a response from the user, remove the mark from the checkbox.
      Note: If you are adding more than one user to a parallel approval workflow group, the Ball In Court Responsibility will shift to the next workflow group after all of the people marked required in the group submit a response to the submittal.

    • Role. Select Approver or Submitter from the list. See What is the difference between a submitter and approver in submittals?
      Notes:* To be designated as an approver, the person must exist in the Project level Directory tool (see Add a User Account to the Project Directory) and must also be granted 'Admin' or 'Standard' level permissions to the Submittals tool (see Set User Permissions for the Submittals Tool).* If you are a user with 'Standard' level permissions to the Submittals tool, you can only add users with 'Admin' level permissions to the workflow.* If you plan to add a Submitter to the submittal, we recommend that you designate a Submittal Manager as the first approver in the submittal's sequential approval workflow. This gives the Submittal Manager an opportunity to ensure the submittal is thoroughly reviewed by your internal stakeholder before it is sent to the users in the next step on the submittal workflow.* If you are a user with 'Admin' level permissions to the Submittals tool, you can add users with either 'Admin' or 'Standard' level permissions to the workflow.
      Note: If you want the submittal workflow to use sequential approval, add only one user to each line item in the workflow. If you want a step in the submittal workflow to use parallel approval, add two or more users to a line item.

    • Due Date. Select a date from the calendar for the submittal response to be due.
      Note: The 'Due Date' field is automatically populated based on the default number of days specified on the Submittals tool's Configure Settings page. See Configure Settings: Submittals Tool. The due date also respects which days are set as 'working days' for the project. See Set Project Working Days.

  2. Click Add Step.

  3. Repeat these steps to add another user to the workflow.

  4. If you want to change the order of the workflow steps, do the following:

    1. Grab the line item by the vertical grip (⋮⋮).

    2. Use a drag-and-drop operation to move the line item into the desired order.

      submittals-change-order-table.png

Update and Send the Submittal for Review

When finished with the steps above, choose one of these options:

  • To save your changes without sending an email to members of the submittal workflow, distribution list members, and submittal manager, click Create.
    OR

  • To save your changes and to send an email notification to alert the members of the submittal workflow and to alert the members of the distribution list, click Create & Send Emails.