Things to Know
Background
Each of Procore's available ERP connectors perform the basic function of syncing data between the ERP system and Procore, usually in the same way as other connectors. However, each connector has a unique set of items it can sync, and the way those items are synced will vary based on how that ERP system and its corresponding integration are built to function.
Yardi Voyager®, like all ERP integrations, has some key considerations, limitations, and things to know about how each Procore object is synced. Those considerations, limitations, and things to know are outlined in the table below according to tool or item being synced.
Things to know about the {{integrations_yardi}} Connector
Procore Item or Setting | Considerations, Limitations, and Requirements |
configuration settings & sync schedule |
|
Cost Codes/Cost Types | Add Cost Codes to import to Procore
|
projects | Important
Add a Yardi Voyager® job to Procore
Export a project from Procore
Enable ERP Job Cost Transaction Syncing - Additional Information:
Sync Job Cost Transactions - Additional Information
|
SUB JOBS |
|
PROJECT LEVEL work breakdown structure (wbs) | Yardi Voyager® jobs imported as Sub Jobs will have cost codes at the sub job level. |
BUDGET |
|
BUDGET CHANGES | You can export budget changes with Sub Jobs on the Schedule of Values (SOV) line items. |
companies | Import Companies to Procore
Adding a Yardi Voyager® Vendor to the Procore Directory
Archiving a Vendor in Procore - Additional Information
|
commitments | Yardi Voyager® supports the sync of subcontracts and purchase orders. You must contact your Integration Implementation Specialist or ERP support before beginning to sync purchase orders so that the appropriate configurations can be enabled. Exporting a Commitment to Yardi Voyager®
|
commitment change orders (cco) | Yardi Voyager® supports the sync of CCOs for subcontracts and purchase orders. Accept or Reject a CCO for Export to Yardi Voyager®
Export a CCO to Yardi Voyager®
|
commitment invoices | Yardi Voyager® supports the sync of subcontractor invoices. Purchase order invoices are not supported at this time. Export Subcontractor Invoices from Procore to Yardi Voyager®
|
direct costs/Payments Issued | Import Direct Costs and Invoice Payments across all projects from Yardi Voyager® to Procore
|
PROJECT LEVEL work breakdown structure (wbs) | Yardi Voyager® jobs imported as Sub Jobs will have cost codes at the sub job level. |
BUDGET |
|
BUDGET CHANGES | You can export budget changes with Sub Jobs on the Schedule of Values (SOV) line items. |