Resource Management

Objects in the Resource Management Dataset

Not all objects are available to all companies. See below for what objects are in the dataset and who they are available to. Not all users see all objects in a company, please see permissions for more information on how a user’s tool permissions impact what objects are available to them in the dataset.

Area

Object

Available to

Core

Company (Vendor)

All Companies

Crew

Companies with access to Resource Management

Employee

All Companies

Project

Budget

Budget Change

Companies with access to Financials

Budget Change Adjustment Line Item

Budget Line Item

All Companies

Budget Code

Budget Code

All Companies

Change Events

Change Event

Companies with access to Financials

Change Event Line Item

Commitments

Commitment

Companies with access to Financials

Commitment Line Item

Commitment Change Orders

Commitment Change Order

Companies with access to Financials

Commitment Change Order Line Item

Commitment Potential Change Order

Commitment Potential Change Order Request

Commitment Change Order Markup

Direct Costs

Direct Cost

Companies with access to Financials

Direct Cost Line Items

Prime Contracts

Prime Contract

Companies with access to Financials

Prime Contract Line Items

Prime Contract Change Orders

Prime Contract Change Order

Companies with access to Financials

Prime Contract Potential Change Order

Prime Contract Change Order Request

Prime Contract Change Order Line Item

Prime Contract Change Order Markup

Production Quantities

Actual Production Quantity

Companies with access to Resource Management or Financials

Budgeted production Quantity

Change Event Production Quantity

Companies with access to Financials

Prime Contract Change Order Production Quantity

Resource Planning

Resource Planning Assignment

Companies with access to Resource Planning

Resource Planning Group

Resource Planning Job Title

Resource Planning People

Resource Planning Project

Resource Planning Request

Resource Planning Time Off

Resource Planning Roles

Resource Planning Tags

T&M Tickets

T&M Ticket

Companies with access to Resource Management or T&M Tickets

T&M Ticket Equipment

T&M Ticket Labor

T&M Ticket Material

T&M Ticket Subcontractor

Timecard Entry

Timecard Entry

Companies with access to Resource Management

How are objects in the Dataset Joined?

Objects that have a relationship are linked by a join. When two objects in Enhanced Reporting are joined, they appear in the same row in a report. For example, a commitment change order is joined to a commitment, and they will appear in the same row. Sometimes, two objects aren’t directly joined, but are joined through a third object. In this case, a field from that third object must be added to a report to show the connection between the first two. For example, an Inspection and an Action Plan Item do not have a direct relationship, but a field from an Action Plan Line Item Record that does have a direct relationship with both will be added to a report, all three objects will appear in the same line.

The table below shows the joins of the objects in the dataset. To determine if two objects are joined, search for one across the top and the other on the side. The cell that corresponds to the column and row of the objects tells you if they are joined.

  • If the cell shows “Join”, the objects are joined directly and fields from these objects will appear in the same row.

  • If the cell shows “Join (through third object name),” the objects are indirectly joined through a third object. A field from that third object must be added to the report to see the data in the same row.

  • If the cell shows “No join,” the objects do not have a relationship and data will not appear in the same row (the exception to this is if only measures from these objects have been added to the report).

Join Table

Join Table Workforce Management

Join Table CSS for reuse

Click to View Join Table

Legend

Join

Join through numbered object

* Join through any line item object

** Join through any line item object except Budget

  1. Actual Production Quantity

  2. Budget Code

  3. Budget Line Item

  4. Budgeted Production Quantity

  5. Change Event

  6. Change Event Line Item

  7. Change Event Production Quantity

  8. Commitment

  9. Commitment Change Order

  10. Commitment Change Order Line Item

  11. Commitment Change Order Markup

  12. Commitment Change Order Request

  13. Commitment Line Item

  14. Commitment Potential Change Order

  15. Company (Vendor)

  16. Crew

  17. Direct Cost

  18. Direct Cost Line Item

  19. Employee

  20. Prime Contract

  21. Prime Contract Change Order

  22. Prime Contract Change Order Line Item

  23. Prime Contract Change Order Markup

  24. Prime Contract Change Order Production Quantity

  25. Prime Contract Change Order Request

  26. Prime Contract Line Item

  27. Prime Contract Potential Change Order

  28. Project

  29. Project Roles

  30. Resource Planning Assignment

  31. Resource Planning Group

  32. Resource Planning Job Title

  33. Resource Planning People

  34. Resource Planning Project

  35. Resource Planning Request

  36. Resource Planning Time Off

  37. Resource Planning Roles

  38. Resource Planning Tags

  39. T&M Ticket

  40. T&M Ticket Equipment

  41. T&M Ticket Labor

  42. T&M Ticket Material

  43. T&M Ticket Subcontractors

  44. Timecard Entry