Set Up the Procore Labor Productivity Cost Budget View

Objective

To learn how the 'Procore Labor Productivity Cost' budget view can leverage data from Procore's Resource Tracking tools to view real-time labor productivity costs in Procore's Budget and Reports tools.

Background

The 'Procore Labor Productivity Cost' budget view provides project teams with the ability to include production quantities on the project's budget. See What are 'production quantities'? Building off the Real-Time Labor Costing feature, the 'Procore Labor Productivity Cost' budget view is designed to provide self-performing and specialty contractors with the ability to gain greater insight into your project's production rates to make better decisions that maximize profit margins. With this release, you can:

  • Add and import production units to a project's budget in Procore's Financial Management tools: Budget, Change Events, and Change Orders.

  • Collect production units from field personnel with Timecard Entries in the Daily Log and both the Timecards and Timesheets tools.

  • Track and compare budgeted production units to installed production units using Procore's Budget and Reports tools.

By default, Procore provides its users with a standard 'Procore Labor Productivity Cost' budget view, which is available to your company's Procore Administrator in the Company level Admin tool.

Example iconExample

Procore Labor Productivity Cost Budget View in the Budget Tool

The illustration below shows you the recommended layout for the 'Procore Labor Productivity Cost' budget view, as it will look when applied to your project's Budget tool.

budget-procore-labor-prod-cost-view.png

Default Columns

The following table details the default columns provided with the 'Procore Labor Productivity Cost' budget view. In the Description column, the following symbols represent the operator for a calculation:

  • add (+)

  • subtract (-)

  • multiply (*)

  • divide (/)

Column Name

Column Type

Column Format

Column Description

Column Configuration

Revised Budget

Calculated

Currency

Shows the Original Budget amount, plus the Budget Change amount, plus the Approved COs amount.

Original Budget Add (+) Budget Changes Add (+) Approved COs

Direct Costs

Source

Currency

Shows the Direct Costs amount.

Source Category: Direct Costs Source: Direct Costs Source Filtering: Status = Pending, Revise and Resubmit, Approved

Direct Costs Unit Cost

Source

Number

Shows the actual cost per unit for direct costs.

Direct Costs Divide (/) Direct Costs Unit Qty

% Budget Complete

Calculated

Percent

Shows how much of the current budget amount for the budget line item is estimated to be used based on the real-time labor hours and actual labor cost.

Estimated Cost w/ Timesheet Hours Divide (/) Revised Budget

Projected Labor Cost at Completion

Calculated

Currency

Shows the projected labor cost at completion for the budget line item.

Projected Hours at Completion Multiply (*) Direct Costs Unit Cost

Projected Labor Cost Over/Under

Calculated

Current

Shows the Revised Budget minus the Projected Labor Cost at Completion.

Revised Budget Subtract (-) Project Labor Cost at Completion

Revised Budgeted Unit Qty

Calculated

Number

Shows the Budget Production Qty plus the Approved COs Production Qty.

Budget Unit Qty Add (+) Approved CO Units

Budget UOM

Standard

n/a

Shows the Unit of Measure (UOM) for the budget line item.

n/a

Timesheet Hours 1

Source

Number

Shows all Timecard Entry Hours. You can optionally apply Status filters to narrow the data in the view.

Source Category: Timecard Entry Hours Source: Timecard Entry Hours Filtering: None

% Hours Used

Calculated

Percent

Shows how much of the current budget unit qty (labor hours) have been used based on time submitted in Procore.

Timesheet Hours Divide (/) Revised Budget Unit Qty

Earned Hours

Calculated

Number

Shows the number of labor hours earned (merited) based on the work produced to date for that cost code.

Revised Budget Unit Quantity Multiply (*) % Complete Production

Projected Hours at Completion

Calculated

Number

Shows the estimated labor hours needed to complete production for the cost code based on the work produced to date.

Timesheet Hours Divide (/) % Complete Production

% Complete Production

Calculated

Percent

Shows the percentage of the production quantity has been installed to date of the current budgeted production quantity for the cost code.

Actual Qty Installed Divide (/) Revised Budgeted Production Qty

Production UOM

Source

n/a

Shows the UOM for the budgeted production quantity (i.e., for the cost code on the line item).

Source Category: Production UOM Source: Budgeted Production UOM Source Filtering: n/a

Revised Budgeted Production Rate

Calculated

Number

Shows the actual budgeted production rate based on labor hours and installed quantities to date.

Revised Budgeted Production Qty Divide (/) Revised Budget Unit Qty

Actual Production Rate

Calculated

Number

Shows the actual budgeted production rate based on labor hours and installed quantities to date.

Actual Qty Installed Divide (/) Timesheet Hours

Variance Production Rate

Calculated

Number

Shows the difference between the current budgeted production rate and the actual production rate. A positive number indicates you are performing faster than expected. A negative number indicates you are performing slower than expected.

Actual Production Rate Subtract (-) Revised Budgeted Production Rate

1 The 'Labor Productivity Cost' budget view is only available to customers using Procore's Resource Tracking tools. However, the 'Timesheet Hours' column can be added to other budget views. To learn how to add the column, see Can we import our third-party timecard entries to work with the 'Timesheet Hours' column in Procore's Budget tool?

Things to Consider

Prerequisites

  • Verify that the Timesheets tool is active in your company's Procore account.
    Note: To do this, navigate to the Company Admin tool. Under Company Settings, click Account Information. Under Resource Management, verify that Timesheets is 'Licensed.'

  • Assign the Default Cost Type for timecard entries in the Company level Timesheets tool. See Configure Settings: Company Level Timesheets.

  • Add the following tools to the Project Tools menu. See Add and Remove Project Tools.

    • Direct Costs

    • Prime Contracts

    • Optional : Timecards

    • Timesheets

    • Budget

Steps

  • Step 1: Create a New Budget View

  • Step 2: Optional: Customize the Budget View

  • Step 3: Preview the Budget View

  • Step 4: Assign the Budget View to a Procore Project

Step 1: Create a New Budget View

  1. Navigate to the Company Admin tool.

  2. Under Tool Settings, click Budget.

  3. Click Set Up New Budget View.
    set-up-new-budget-view.png

  4. Under Standard Views, highlight Procore Labor Productivity Cost.
    procore-labor-productivity-cost-view.png

  5. Click Create.

  6. Name your view as follows:

    • View Name. Enter a name for your new view. In this example, we named it: Labor Productivity Cost

    • View Description. Enter a description for your view. In this example, we entered: Recommended view for labor cost productivity report

  7. Click Configure Columns.
    This opens the Configure Columns window pictured below. From this point, continue with Step 2: (Optional) Customize the Budget View.

Step 2: Optional: Customize the Budget View

If you want to customize the Procore Labor Productivity Cost budget view, you can click the Configure Columns button. This opens the Configure Columns window, which allows you to edit the budget view. To learn about your editing options, see Configure the Columns for a Budget View in the Set Up a New Budget View tutorial. When you are finished, click the 'x' in the Configure Columns window to close it.

Step 3: Preview the Budget View

After closing the Configure Columns window, the system returns you to the new budget view's window. Under Column Configuration, you can get an idea of how your budget view will look in Procore by selecting a project from the Preview with Project drop-down list.

Step 4: Assign the Budget View to a Procore Project

  1. In the 'Procore Labor Productivity Cost' view window, place checkmarks next to project boxes of your choice in the Assign to Projects list.

    assign-to-projects.png

    • To assign the budget view to all of your company's Procore projects, place a checkmark in the All Projects Selected box.
      Notes:* For companies using the ERP Integrations tool, you will see the 'All Project Using ERP Direct Costs' checkbox.* You may also see the 'All Projects Using Procore Direct Costs' checkbox. However, it only appears when the Direct Costs tool is enabled on the project.

    • To assign the budget view to one (1) or more projects, place a checkmark next to the desired projects.

  2. Click Done.

Tip icon Tip

After completing all of the above steps, you can provide your project teams with instructions for applying the budget view to their project budgets. For details, see Apply the View, Snapshot, Group, and Filter Options on a Budget View.