Add Budgeted Production Quantities

  1. Navigate to the project's Budget tool.

  2. Click the Production Quantities tab.

  3. Click Add Line.

  4. Under Budgeted Production Quantities, do the following:

    • Cost Code
      Enter the cost code that corresponds to the budgeted production quantity for that cost code. These entries should exactly match the cost codes in your Procore project. If you enter a cost code that doesn't exist, the import will fail. Cost codes can be added as segment items in Procore's Work Breakdown Structure.

    • Qty
      Enter the budgeted quantity for that cost code using whole numbers.

    • **UOM
      Select a Unit of Measure (UOM) from the drop-down list. To learn about the default selections in this list, see Which units of measure are included in Procore's master list? and Add a Unit of Measure to the Unit of Measure Master List.

      Note icon Note

      You cannot add line items for budgeted production quantities with UOMs in the 'Time' category in the Production Quantities tab.

  5. Click Save.