Enable Labor Productivity

  1. Navigate to the project's Admin tool.

  2. Click the General tab under Project Settings.

  3. Scroll to Advanced.

  4. Mark the Labor Productivity for Budget, Change Events, and Change Orders check box.

    admin-advanced-enable-labor-productivity.png

  5. Click Update.