Which Procore project tools update data in the Field Production Report?
NoteFor projects using Procore's Resource Tracking tools under 'Resource Management' who have created custom segment objects in Procore's Work Breakdown Structure, please be aware that the custom segment objects are not yet supported in Procore's Resource Tracking tools. To learn more, see Are custom segments compatible with Procore's Resource Tracking tools?
For projects using Procore's Resource Tracking tools under 'Resource Management' who have created custom segment objects in Procore's Work Breakdown Structure, please be aware that the custom segment objects are not yet supported in Procore's Resource Tracking tools. To learn more, see Are custom segments compatible with Procore's Resource Tracking tools?
Answer
The Field Production Report provides Procore users with the ability to compare a construction project's budgeted production quantities with its installed production quantities. With the appropriate permissions, you can view this report with the project's 360 Reporting or Timesheets tool. See View a Field Production Report and Which data columns are in a Field Production Report?
To add and update the production quantities in the Field Production Report, you can choose from these methods:
Add Budgeted Production Quantities
Add budgeted production quantities to the Production Quantities tab in the Budget tool. See Add Budgeted Production Quantities to a Project's Budget.
Import budgeted quantities using the 'Budgeted Quantities' tab in the downloadable Microsoft Excel template. See Import a Budget.
Note: If the Timesheets tool is enabled on the project, you can also import budgeted production quantities using the downloadable Microsoft Excel template on the 'Unit Quantity Based Budget' page of the Admin tool. See Import a Unit Quantity Based Budget.
Add Installed Production Quantities
Add installed production quantities to a timesheet from the Procore web application, Procore for Android, or Procore for iOS. For details, see:* Add Quantities to a Timesheet* Add Quantities to a Timesheet (iOS)* Add Quantities to a Timesheet (Android)
Import installed production quantities into the Budget tool using a downloadable Microsoft Excel template. See Import Installed Production Quantities for the Labor Productivity Cost Budget View.
Note: Keep in mind that Daily Log productivity entries (see Create Productivity Entries) and quantity entries (see Create Quantities Entries) do not interact with the 'Procore Labor Productivity Cost' budget view at this time.
Update Production Quantities:
Add production quantities to a budget from a change event. See Record Changes to Production Quantities in a Change Event.
If your project's prime contract is set to use a 2-tier or 3-tier change order setting, add production quantities by creating a Prime Potential Change Order (Prime PCO). See Record Changes to Production Quantities on a Potential Change Order for a Prime Contract.
If your project's prime contract is set to use a 1-tier change order setting, add production quantities by creating a Prime Contract Change Order (PCCO). See Create a Prime Contract Change Order.
Notes
For customers using Procore's Resource Tracking and Project Financials tools, production quantities and hours entered on your project's change orders automatically updates data in these Procore features, when change orders are placed in the 'Approved' status:
The Procore Labor Productivity Cost budget view. See Set Up the Procore Labor Productivity Cost Budget View.
The Field Production Report. See Set Up a Field Production Report.
To learn about the data columns in this report, see Which data columns are in a Field Production Report?
To learn about the Procore tools that interact with this report, see